07/06/2019 – Site Setup Begins in Herschel

Main contractors, P F Burridge, arrived on site today to begin site setup. The AV team have also stripped the existing audio visual equipment out of Lecture Theatres 1, 2 and 3 which will be either recycled or reused elsewhere on campus.

Lecture Theatre 1 closed for refurbishment.
Lecture Theatre 3 AV removed.
Lecture Theatre 1 AV removed.
Lecture Theatre 1 site setup commencing.