Cassie Building room 2.33 is complete and back in use. Unfortunately, due to a delay with the seating manufacturer, the completion of room 2.32 has been delayed one week and induction activities scheudled to take place in the room have been relocated.
23/09/19 – Herschel Building Completion
20/09/19 – Final Touches in the Herschel Building
11/09/19 – Seating Installation in Herschel Building
06/06/2019 – Ready for the seating in Herschel Lecture Theatres
Decoration and flooring has been completed in Lecture Theatres 1, 2 and 3 ready for the new seating to be installed on from Monday 9th September.
The flooring in the Curtis Auditorium will be completed next week with the seating installation commencing on 14th September.
The AV installation will continue in the Curtis Auditroium and the projection booths throughout next week with testing and commissioning taking place the week after.