Decoration and flooring has been completed in Lecture Theatres 1, 2 and 3 ready for the new seating to be installed on from Monday 9th September.
The flooring in the Curtis Auditorium will be completed next week with the seating installation commencing on 14th September.
The AV installation will continue in the Curtis Auditroium and the projection booths throughout next week with testing and commissioning taking place the week after.