Cassie Building room 2.33 is complete and back in use. Unfortunately, due to a delay with the seating manufacturer, the completion of room 2.32 has been delayed one week and induction activities scheudled to take place in the room have been relocated.
23/09/19 – Herschel Building Completion
20/09/19 – Final Touches in the Herschel Building
11/09/19 – Seating Installation in Herschel Building
06/06/2019 – Ready for the seating in Herschel Lecture Theatres
Decoration and flooring has been completed in Lecture Theatres 1, 2 and 3 ready for the new seating to be installed on from Monday 9th September.
The flooring in the Curtis Auditorium will be completed next week with the seating installation commencing on 14th September.
The AV installation will continue in the Curtis Auditroium and the projection booths throughout next week with testing and commissioning taking place the week after.
29/08/2019 – Decoration Nears Completion in Cassie
28/08/19 – AV Installation Commences in Herschel
Cassie Building Teaching Spaces Refurbishment
Cassie Building rooms 2.32 and 2.33 are currently being refurbished.
Teaching room 2.33 is being decorated and fitted with new AV equipment to bring it up to current standards and Lecture Theatre 2.32 is being reconfigured to provide improved accessibility (including wider doors and a new induction loop) and will be fitted with collaborative ‘turn-and-learn’ style seating which can be viewed here: Cassie 2.32: New Layout
Feedback on the new lecture theatre will be gathered and used to inform upcoming capital projects, in particular the Stephenson Building refurbishment. Details on how to provided feedback will be circulated to all timetabled users in the coming academic year.
29/07/2019 – High Level Works in Herschel
The high level works including new ventilation, lighting, ceilings and decoration are nearing completion. The scaffolding crash-decks will be removed from Thursday 1st August.
Installation of the new acoustic panelling has also commenced in Lecture Theatre 1.
The first fix power and data installation is also complete and once the crash decks are removed, the new raised floors will be installed.
09/07/2019 – Change to Herschel Building Lecture Theatre’s 1, 2 and 3
Following strip out and investigative works in the lecture theatres, it has not been possible to channel the floor for new cabling as expected and an alternative solution has been worked up to overcome the unforeseen issue. This will allow the lecterns to be relocated and desk-top power to be installed as originally planned.
The revised proposal includes raising the floor of all three lecture theatres by 100mm to accommodate the new cabling beneath. Ramped access will be installed at all entrances with automatic doors (operated by push pads).
The revised layout can be viewed here: Herschel_Revised Layout
The project remains on programme with the first bookings scheduled for Monday 23rd September 2019.