I’m please to write that we’ve now completed the first three migrations, meaning that all three departments in Claremont Tower are now utilising the new core network.
The next three dates are as follows:
| Devonshire Building | 07:00-09:00 29-05-2014 |
| General Hospital/Biomedical Research Building | 10:00-12:00 04-06-2014 / 05-06-2014 |
Please see the latest version of the schedule below:
http://connect.ncl.ac.uk/download/DC_-_Network_Upgrade_Schedule.pdf