Wolfson Completed, Mertz Court Scheduled

We are pleased to announce that the migration of Wolfson building was successful on 31st October.

Mertz Court has now been scheduled for 7th November between 0700-0900. This work will involve around 20 solid minutes of downtime followed by a period of instability while we perform some admin work. Armstrong building is scheduled following the completion of Mertz Court and will take place the week commencing 10th November.

Fine Art Completed, Wolfson moved forward

We are pleased to announce that the migration for Fine Art building has been successfully competed on 24th October.

We have decided to move forward the planned migration of Wolfson building to 31st October between 0700-0900. This work will involve around 20 solid minutes of downtime followed by a period of instability while we perform some admin work. Mertz Court’s migration will now take place the following week.

Merz Court Scheduled

After the competition of Fine Art’s building on Friday 24th, Merz Court’s migration is scheduled for 30th October between 0700-0900. This work will involve around 20 solid minutes of downtime followed by a period of instability while we perform some admin work.

Drummond Complete, Fine Art Planned

We are pleased to confirm that the migration for Drummond building was successfully completed on 14th October.

Fine Art Building is scheduled next, with its migration scheduled for
Friday October 24th between 0700-0900. This work will involve around 20 solid minutes of downtime followed by a period of instability while we perform some admin work.

Following this work the next sites scheduled for migration are:

Building Week Commencing
Merz Court 27-10-14
Wolfson Building 03-11-14
Armstrong Building 10-11-14

 

Paul O’Gorman and Herschel Completed

Following our 2 week freeze for registration, I’m pleased to announce that we have now successfully completed the migrations of Paul O’Gorman Building on 3rd October and Herschel Building on 7th October.

We are pleased to announce the migrations are running to schedule and more information on the next buildings will be published shortly.

Paul O’Gorman Building scheduled

The Paul O’Gorman Building  its migration scheduled for Friday 3rd October between
0700-0900. This work will involve around 20 solid minutes of downtime
followed by a period of instability while we perform some admin work.

Following this work the next two sites to be migrated will be:

Building Week Commencing
Herschel Building 06-10-14
Armstrong Building 13-10-14