We are pleased to confirm that the migration for Drummond building was successfully completed on 14th October.
Fine Art Building is scheduled next, with its migration scheduled for
Friday October 24th between 0700-0900. This work will involve around 20 solid minutes of downtime followed by a period of instability while we perform some admin work.
Following this work the next sites scheduled for migration are:
| Building | Week Commencing |
| Merz Court | 27-10-14 |
| Wolfson Building | 03-11-14 |
| Armstrong Building | 10-11-14 |