Following our 2 week change freeze for clearing related activities, I’m pleased to announce that we have now successfully completed the migrations of Medical School Leech Building, Old Library Building and Architecture Building.
Following another 2 week break for Registration related activities the following sites are planned:
| Building | Week Commencing |
| Paul O’Gorman Building | 29-09-14 |
| Herschel Building | 06-10-14 |
| Armstrong Building | 13-10-14 |
More information around the Paul O Gorman migration will be published shortly.