Paul O’Gorman and Herschel Completed

Following our 2 week freeze for registration, I’m pleased to announce that we have now successfully completed the migrations of Paul O’Gorman Building on 3rd October and Herschel Building on 7th October.

We are pleased to announce the migrations are running to schedule and more information on the next buildings will be published shortly.

Paul O’Gorman Building scheduled

The Paul O’Gorman Building  its migration scheduled for Friday 3rd October between
0700-0900. This work will involve around 20 solid minutes of downtime
followed by a period of instability while we perform some admin work.

Following this work the next two sites to be migrated will be:

Building Week Commencing
Herschel Building 06-10-14
Armstrong Building 13-10-14