Phase 2 complete

Cassie & Drummond buildings were migrated successfully on Tuesday and the last of the halls have been moved onto the production wireless controllers today completing phase 2 of the migration. This means all of the new wireless access points (over 2000) are running on the final production service.

There are a few dozen access points that have been installed but are not working correctly which will be addressed in the coming weeks and over the Summer.

It is unlikely we will be able to get more phase 3 buildings on-line before Module selection and Exams force a change freeze. We will update the schedule and this blog once we have more information.